Highway KR under I-94 is now open.
Highway A under I-94 will close Monday Aug. 5 and Tuesday Aug. 6 from 5:30 a.m. to 11:00 a.m.
On Saturday August 10, Highway KR will reopen from Lake Michigan to Union Grove. At that time the intersecions of Highway KR and 100th Ave. as well as 113th Ave. will be closed. These intersections will remain closed until the east bound lanes are constructed, which is expected to be completed in late October or early November.
The Village of Mount Pleasant will be resuming sewer work on Highway KR in the area of the Kilbourn Ditch after KR opens. Motorists will see large pumps operating 24 hours a day until the work is completed.
Highway E will reopen under I-94 in the middle of September.
The work Highway KR east of Highway H will not start before July of 2020 as plans are finalized.