Highway KR
The widening of Highway KR (First Street) is progressing. The topsoil stripping and excavation for the westbound of the roadway, between Union Pacific Railroad and Pike River has been completed. All traffic on Green Bay Road has been switched to the northbound lanes near the intersection. Decking on the eastbound lanes of the Pike River bridge has been completed.
Current Project Work
- Deck pour on eastbound Pike River bridge
- WIS 31 southbound pavement removals and roadway excavation
- Continued retaining wall construction at Canadian Pacific Railroad
- Excavation for roadway between Pike River to Union Pacific Railroad
- Storm sewer installation between Pike River and Union Pacific Railroad
- Continued retaining wall construction at Canadian Pacific Railroad
- Continued storm sewer installation between Pike River and Union Pacific Railroad
Coming up next
- Continued storm sewer installation between Pike River and Union Pacific Railroad
- Topsoil stripping and excavation for roadway for westbound County KR, between Green Bay Road and Pike River
- Storm sewer installation on southbound Green Bay Road
- Piling at Union Pacific Railroad for westbound County KR bridge
Highway H
The erosion control on Highway H (88th Avenue) has been completed.
Current Project Work
- Installing erosion control
- Pavement removals
- Crushing asphalt
- Roadway excavation
- Storm sewer
Upcoming Project Work
- Continued storm sewer
- Continued pavement removals
- Continued crushing asphalt
- Placing base aggregate
- Continued roadway excavation